Building Update | June 9, 2016

The roof, wood framing, insulation, and windows are pretty much done! Workers are making great progress on the HVAC, electrical, drywall, and exterior siding. Keep praying for God’s favor as we build His church!
IMG_2429
IMG_2427
IMG_2428


Building Update | May 26, 2016

Things continue to move along at our new property on Hartman Rd. The entire building is almost insulated and drywall is starting to be hung. They’ve also made great progress on the exterior siding and decorative pieces in the lobby.
IMG_2401
IMG_2400
IMG_2399
IMG_2398


Building Update | May 13, 2016

The windows are starting to be installed and siding is being prepped! Last Thursday, many of our people came out for a tour of the facility and to participate in writing prayers on the studs before the drywall goes up.
IMG_2358
IMG_2360
IMG_2361
IMG_20160513_144328_01
IMG_20160513_144356_01
IMG_20160513_144406_01


Building Update | April 20, 2016

Things are progressing nicely on the new building. All the exterior and interior walls are up, roofers are starting this week, and the electricians will be starting to wire this week!
IMG_2253
IMG_2261
IMG_2259
IMG_2257
IMG_2256
IMG_2255


Building Update | April 5, 2016

The view from inside our new lobby and auditorium. This place is massive!
 


Building Update | March 16, 2016

Video update with Pastor Lance.
 


Building Update | March 8, 2016

Another big week at the construction site! The steel has arrived and the crew will be working on putting up the sanctuary, exterior, and bathroom walls. To see more pictures, visit our website at www.rlcwadsworth.com
IMG_2026
 


Building Update | March 2, 2016

The walls are going up! The construction crew has started framing the walls in the children’s wing of the new building. These are going to be some sturdy walls since they are using 2×6 boards instead of 2×4’s in order to hold the weight of the steel roof. That means extra insulation which means quieter classrooms! I can hear all the children workers rejoicing now. Steel will be arriving on Monday and they are putting the finishing touches on the water line. For more photos, visit us online at www.rlcwadsworth.com.
IMG_1932
 


Building Update | February 23, 2016

All the concrete has been poured and the lumber will be arriving this Thursday. Before you know it the walls will be going up!
900x1600
720x1280


Friday | February 19, 2016

Concrete is being poured for the children’s wing today! They are still working on the water line but progress is being made in all areas of construction. Visit http://www.rlcwadsworth.com/building-updates for more pictures.