Building-Updates-black
 
 

Wednesday | February 17, 2016

We have officially gone vertical! The steel structure for the entrance is up and they are putting in our water line. By the end of the week, the contractors hope the weather is good enough to pour concrete for the children’s wing. See more pictures at http://www.rlcwadsworth.com/building-updates.
IMG_1911
 


Thursday | February 11, 2016

Craven Construction sent us this awesome video showing all the work that has been done on our property. Take a moment, watch, and say a prayer of thanks for all that God’s done and will continue to do through Radiant Life Church!
 


Tuesday | February 2, 2016

Thanks to this great weather, the builders were able to pour concrete in February! Here are some great pictures as they pour the main auditorium, lobby, and gym.
DJI00317
DJI00322
DJI00324
DJI00334


Tuesday | January 5, 2016

Finishing up all the foundation this week and we wanted to make sure we got everyone’s lists from the “What Are You Leaving” sermon Pastor Lance did for the last message in the old building. Electricians, plumbers, and concrete guys are also hard at work!
IMG_1717
IMG_1715


Wednesday | December 16, 2015

Footers are ready to be poured!
DJI_0039
DJI_0035


Monday | October 26, 2015

The contractors got a brand new toy and wanted to test it out on our property. We think you’ll agree it’s pretty cool!
DJI00271
DJI00274


Tuesday | October 20, 2015

Pastor Lance is a little excited about the drainage pond.
 


Thursday | October 1, 2015

Breaking ground ceremony at our new property.
 


Tuesday | September 8, 2015

We are so excited for our future building! Here are some of the renderings of what it will look like when everything is completed.
rlc_front_edit-2
RLC-North-Edit


Saturday | August 15, 2015

Our new temporary location is all set up and ready to go!
 
11219724_1049836618362719_4743387648530543912_n